Audit planning : September-October 2009
On-site examination : November 9-13, 2009
Clearance draft to IPM and IR for comments : February 12, 2010
Management Action Plan finalized : Still to be developed
Recommended for approval by Audit Committee : June 4, 2010
Report approved by Deputy Minister : June 4, 2010