Review of the Handling of Public
Money Project — Final Report
5.0 Management Response and Action Plan
Recommendation/Management Response
(4 of 11)
| Recommendation / Management Response | Action Plan | Office of Primary Interest | Planned Implementation Date |
|---|---|---|---|
| 4. It is recommended that F&A and DDN (in consultation with the CPCs) discuss with IMTB system oriented modifications to the CPC system and the CRS, to simplify the process of sending a refund to the correct address and payer and to upgrade CRS to capture who paid the fees (since this feature exists in the CPC system). To ensure consistency, when a change is proposed—for example, with regard to how a receipt is handled—it is recommended that both CPC and CRS system teams work together to ensure the same process and therefore the same service is available to the clientele. Management Response Management agrees with this recommendation. |
Documentation of current process |
DDN (Sydney) | April 21, 2002 |
| Confirmation of system capacity | IMTB | April 30, 2002 | |
| Options for streamlining the process | IMTB and DDN (Sydney) | June 30, 2002 | |
| Development and implementation of simplified refund process within CRS | IMTB and DDN (Sydney) | September 30, 2002 |
- Date Modified: