Review of the Immigration Control
Officer Network – Final Report
4.0 Management Response and Action Plan (10/12)
| Recommendation / Management Response | Action Plan | Office of Primary Interest | Planned Implementation Date |
|---|---|---|---|
|
10. (section removed) Management Response Management agrees that such an overlap would be ideal.
|
By April 25, 2002, SEZ will draft and circulate
transition guidelines for ICO posts that will be included in the
ICO handbook being developed by SEZ. The group agrees (section removed). It was agreed that SEZ, BCO and RIR would examine the feasibility of (section removed) and temporary duty assignments, in advance of (section removed), on a case by case basis. |
SED in consultation with BCD and RID | April 25, 2002 |